Reference Years

Key takeaway: The model seeds projections with a synthetic reference year — each calendar month drawn from the historical year (2016 to 2025) whose simulated prices sit closest to the ten-year median for each state.

A reference year is a representative historical period used to seed future weather and outage profiles. It drives demand, solar and wind load factors, hydro, generation outages, and transmission outages in the forecast.

A synthetic reference year is a calendar year built by stitching together months drawn from different historical years — January might come from one year, February from another, March from a third, and so on. The same month-to-year mapping is applied to every forecast year, so the seeded weather pattern repeats annually across the projection.

Months are chosen to match the ten-year median as closely as possible

For each calendar month and state, simulated price medians were computed across the last ten years. The ten-year median is the middle price for that state and month across those ten candidate years.

The selection then picks month-year pairs that get each state’s prices as close as possible to this median — formally, minimising the largest percentage gap between simulated and median prices across all states and forecast years (2026 to 2031). The resulting mapping is held fixed across all scenarios and forecast years.

Historical reference year used per month
Historical reference year assigned to each calendar month, held fixed across all scenarios and forecast years

Because the mapping is fixed, year-on-year revenue differences reflect fundamentals rather than seed selection. A small amount of regional bias remains within each forecast year, but materially less than under any single-year choice.

Seeding preserves calendar day-of-year alignment

Each calendar month of the forecast is seeded with weather and outage data from its assigned historical year, preserving calendar day-of-year alignment. For example, 15 March of the forecast is seeded from 15 March of the assigned reference year. The same mapping is applied consistently across demand, renewable traces, hydro, generator outages, transmission outages, and commodity prices.

Months drawn from years prior to the introduction of 5-minute settlement require interpolation of historical settlement data to 5-minute granularity.

Alternative approaches considered

  • Using a single historical reference year: Rejected because no single year produces a typical price across every state at the same time. Any single-year choice imposes a regional price bias that cannot be corrected downstream — for example, 2023 was the strongest single-year candidate but still skewed simulated prices marginally upward in Queensland and marginally downward in Victoria, South Australia, and New South Wales.
  • Cycling between ten historical years: Used by the Australian Energy Market Operator (AEMO) in some of its modelling. Rejected because it becomes unclear whether revenue changes from year to year come from real market fundamentals or from which reference year was assigned to that year.
  • Random sampling from historical distributions: Rejected because adding randomness makes the model harder to interpret, makes it difficult to capture how demand, wind, and solar move together, and obscures whether a year’s revenues reflect real market drivers or sampling noise.